Evacuation Lift Installation

Alconbury Weald, Cambridge

Ecocell Evacuation lift installation was the lift chosen by Cambridge County council to be installed at their new build Headquarters located at Alconbury Weald. The Alconbury Civic hub is an 18 million pound project.

R G Carter Construction has taken almost 3 years to complete the build which has managed to continue with social distancing through the pandemic, it is at the center of a major redevelopment of an old RAF airfield and will be surrounded by a prestigious new housing development which will form a new community.